Infrastructure appraisal: keep economic value separate from the funding plan
A project can be economically worthwhile and financially unfundable, or financially comfortable and economically wasteful. Conflating the two hides which problem you have.

- Byline
- Gambit Reign analysis
- Period covered
- 2023
- Reviewed
- 6 October 2026
- Topic
- Project development
- Reading time
- 5 min read
Key takeaways
- Economic appraisal asks whether a project is worth doing from the perspective of the economy as a whole. Financial appraisal asks whether the money works for the parties involved. They use different prices, different perspectives and different conclusions, and answering one does not answer the other.
- Grants and subsidies are transfers, not resource costs. A transfer changes who pays; it does not change what the project consumes. Counting a transfer as a benefit in an economic appraisal double counts value the project creates elsewhere.
- Legally secured support can legitimately enter the funding case with its terms and counterparty risk assessed. Speculative funding belongs in sensitivities, and the resource cost of the project does not change either way.
Two appraisals, two questions
The European Investment Bank publishes guidance on the economic appraisal of investment projects, which sets out how to assess whether a project delivers value from an economic perspective. [G] The distinction it draws between economic and financial appraisal is the subject of this article, and it is one that projects routinely blur.
Economic appraisal asks whether the project is worthwhile for the economy as a whole. It counts the resource cost of what the project consumes — labour, materials, land, energy — valued at their opportunity cost, and it counts the benefits the project delivers to users and to others affected by it. It is concerned with whether the project makes the economy better off.
Financial appraisal asks a different question: whether the money works for the entities involved. It counts cash flows to and from those entities, at the prices they actually pay and receive, and it is concerned with whether they can fund the project, service any debt, and earn an acceptable return.
The two can disagree, and the disagreements are informative. A project can be economically valuable and financially unfundable, because the benefits accrue to users and the community while the costs fall on the promoter. A project can be financially comfortable and economically wasteful, because it earns revenue by transferring activity from elsewhere rather than creating value. Knowing which situation applies determines what the project actually needs — a funding solution in the first case, a redesign in the second.
Transfers are not resource costs
The most consequential error in infrastructure appraisal is treating a transfer as though it were a resource cost or a benefit.
A grant, a subsidy, a tax or a levy is a transfer. It moves money from one party to another. It does not consume resources and it does not create them. In a financial appraisal the transfer matters enormously, because it changes who pays and how much. In an economic appraisal it does not appear as a benefit at all, because the economy as a whole is neither richer nor poorer for the money having moved.
Counting a grant as a benefit in an economic appraisal therefore double counts. The value the project creates is already counted through the benefits to users; adding the grant counts a transfer on top of it, and inflates the case. Conversely, counting a grant as a cost in an economic appraisal is wrong in the other direction.
The distinction also clarifies a related question that causes confusion: whether a project 'needs' support. Economically, if the benefits exceed the resource costs, the project is worth doing and the question is how to fund it. If they do not, no amount of funding changes that — a transfer can make the finances work but cannot make the project worth doing.
| Aspect | Economic appraisal | Financial appraisal |
|---|---|---|
| Question | Is the project worthwhile for the economy? | Does the money work for the parties involved? |
| Prices used | Opportunity cost / shadow prices where they differ | Prices actually paid and received, including tax |
| Benefits counted | Value to users, and externalities to others affected | Revenue and other cash inflows to the promoter |
| Grants and subsidies | Transfers — excluded from benefits and costs | Legitimate inflows, counted in full |
| Tax and duties | Transfers, excluded | Real cash flows, included |
| Who pays vs who benefits | Explicitly separated — this is the analysis | Both sit with the promoter within its own boundary |
| Typical conclusion | Whether the project should proceed at all | Whether it can be funded and sustained |
This comparison is our own working framework. It summarises the distinction between the two appraisals; it does not reproduce the guidance it references and is not derived from or endorsed by the EIB.
Double counting, in both directions
Double counting in appraisal usually takes one of two forms, and both are common enough to be worth naming.
The first is counting the same benefit twice. Where a project generates a benefit that appears in more than one line — improved accessibility counted both as a user benefit and as a land value uplift, for instance — the value is counted once too many. The discipline is to identify each distinct benefit and count it once, in the line where it most directly arises.
The second is counting a transfer as a benefit, as discussed above. The two errors often appear together: a project counts its grant as a benefit and also counts the activity the grant funds as a benefit, describing the same money as creating value twice.
The remedy in both cases is the same: be explicit about the boundary of the analysis, identify what each line represents, and check that no value appears in two places. An appraisal that states its boundary and its treatment of transfers is straightforward to review; one that does not is difficult to trust even when the arithmetic is correct.
Risk, and where it shows up
Risk appears in both appraisals, and how it is treated matters as much as the base figures.
In economic appraisal, risk attaches to the benefits and costs themselves — whether the demand materialises, whether construction costs more than expected, whether the benefits are realised as predicted. These are usually handled through sensitivity analysis and scenario testing, showing how the conclusion changes as the assumptions move.
In financial appraisal, risk attaches additionally to the funding — whether committed support is received, on what terms, and on time. And here the distinction from earlier applies directly. Support that is legally secured and contractually committed, with defined terms, can properly be included in the funding case; its counterparty risk should be assessed, which means considering the payer's ability and willingness to perform and what happens if a condition is not met. Support that is speculative — untested eligibility, unpublished terms, a benefit dependent on a future administrative decision — belongs in a sensitivity, because including it in the base case would make the case contingent on an outcome the project does not control.
This is a distinction about evidence, not about whether support is legitimate. A project with secured support and sound economics is in a strong position. A project whose case collapses without support that has not yet been granted has an untested assumption at its centre — and the earlier it is identified as such, the more options remain open.
Which appraisal answers which question
The practical value of keeping the two appraisals separate is that each answers a question the decision actually needs.
If the question is whether a public body should support a project, an economic appraisal answers it, because the concern is whether the project creates value for the economy. If the question is whether a promoter can deliver and sustain the project, a financial appraisal answers it, because the concern is cash. If the question is whether a project should proceed at all, both matter, and a project that fails either requires attention that is specific to which one failed.
Presenting them separately, rather than as a single combined case, also makes each reviewable on its own terms. A reviewer can check whether the economic case has correctly excluded transfers and counted benefits once, and separately whether the funding case rests on committed support or on hope. Combined into one figure, both checks become impossible.
Limitations
- This article sets out the distinction between economic and financial appraisal and how to keep them separate. It contains no figures, rates or results for any project.
- The cited EIB guidance is the source of the economic appraisal distinction. This article is not derived from or endorsed by the EIB and does not reproduce its methodology.
- Economic appraisal methodology, discount rates, shadow price conventions and appraisal requirements vary by jurisdiction and by funding body. The applicable approach must be confirmed for the project and the body concerned.
- Nothing here is financial, legal or investment advice. Any funding decision should be supported by appropriately qualified financial and legal advisers.
The next decision
Separate your economic case from your funding case — then decide which one is actually the constraint on your project.
Discuss your projectTaking this into your own project?
Our scoping guide and worksheet walk through the questions that make a brief usable — the decision, the evidence, the options including doing nothing, and what still has to be established. No email required.
Sources
External sources are referenced above by letter. Our own recommendations are identified as such in the text and are not attributed to these sources.
- [G]European Investment Bank — The Economic Appraisal of Investment Projects at the EIB, 2nd edition (28 March 2023)https://www.eib.org/en/publications/20220169-the-economic-appraisal-of-investment-projects-at-the-eib.htm
